Question: Consider the following project. Activity Immediate Processor Activity Time ( days ) A - 6 B - 8 C A , B 5 D B
Consider the following project.
Activity
Immediate Processor
Activity Time days
A
B
C
A B
D
B
E
C
F
C D
G
D
H
E F G
Determine the critical path and determine the estimated completion time of the project.