Question: Consider the following project . Activity Immediate Processor Activity Time A (days ) 8 B 6 A , B 4 D 5 E B 8
Consider the following project . Activity Immediate Processor Activity Time A (days ) 8 B 6 A , B 4 D 5 E B 8 F 7 G C, D E, F 6 a. What is the critical path of the project ? 5 points b. What is the earliest completion time for this project ? 3 points ] c. If activity C is delayed by three days , what is the revised earliest project completion time ? [2 points ]