Question: Consider the following table, Activity Predecessor(s) Predecessor(s) Duration J 4 K 7 J 7 J,K 3 - 3 z o L, M 6 KN 07

Consider the following table, Activity
Consider the following table, Activity Predecessor(s) Predecessor(s) Duration J 4 K 7 J 7 J,K 3 - 3 z o L, M 6 KN 07 a) Draw the Network diagram b) Calculate the critical path and expected duration