Question: Consider the following work breakdown structure: Activity Duration (Days) Optimistic Most Likely Pessimistic Preceding Task -40 41 50 B 59 66 A C D 54

Consider the following work breakdown structure:
Consider the following work breakdown structure: Activity Duration (Days) Optimistic Most Likely Pessimistic Preceding Task -40 41 50 B 59 66 A C D 54 58 32 60 70 41 82 B 44 What is the estimated expected (mean) time for activity D? Multiple Choice 32 days 41 days O 44 days 42 days 40 days