Question: QUESTION 30 Consider the following work breakdown structure for a project: Activity Start Node Finish Node Optimistic Time Most Likely Time Pessimistic Time A 1

QUESTION 30QUESTION 30 Consider the following work breakdown

Consider the following work breakdown structure for a project: Activity Start Node Finish Node Optimistic Time Most Likely Time Pessimistic Time A 1 2 41 50 59 B 1 54 60 2 58 70 32 41 66 82 44