Question: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Precedes Start A,B A C,D B D c E D F

Consider the following work breakdown structure:
Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Precedes Start A,B A C,D B D c E D F E F F End 44 45 42 31 27 50 60 45 40 36 70 56 75 48 49 39 82 58 What is the estimated standard deviation in the time for activity E? Multiple Choice 5 days 1 day 2 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!