Question: Consider the following work breakdown structure: Activity Time Estimates (days) Optimistic Most Likely Pessimistic Start B D E F mm oom Precedes A,B,C D E

Consider the following work breakdown structure:
Consider the following work breakdown structure: Activity Time Estimates (days) Optimistic Most Likely Pessimistic Start B D E F mm oom Precedes A,B,C D E End F End End 38 9e 85 19 91 62 50 99 100 25 100 65 62 108 115 31 115 68 What is the estimated standard deviation in the time for activity E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!