Question: QUESTION 14 Consider the following work breakdown structure: Pessimistic Time Estimates (days) Activity Precedes Optimistic Most Likely Start A,B,C A D 38 50 B E

QUESTION 14 Consider the following work breakdown
QUESTION 14 Consider the following work breakdown structure: Pessimistic Time Estimates (days) Activity Precedes Optimistic Most Likely Start A,B,C A D 38 50 B E 79 115 End 85 100 D F 19 25 E End 91 100 End What is the probability that this project will be completed within 205 days? O 0.2451 62 115 115 31 115 68 62 65 0.9996 0.0823 O 0.7549 0.8413

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!