Question: Consider the following work breakdown structure: begin { tabular } { ccccc } & & multicolumn { 2 } { c } {

Consider the following work breakdown structure:
\begin{tabular}{ccccc}
& & \multicolumn{2}{c}{ Time Estimates (days)}\\
Activity & Precedes & Optimistic & \begin{tabular}{c}
Most \\
Likely
\end{tabular} & Pessimistic \\
\cline {3-5} Start & A, B & - & - & -\\
A & C, D & 44 & 50 & 56\\
B & D & 45 & 60 & 75\\
C & E & 42 & 45 & 48\\
D & F & 31 & 40 & 49\\
E & F & 27 & 36 & 39\\
F & End & 58 & 70 & 82
\end{tabular}
What is the estimated slack time for activity D?