Question: Consider the following work breakdown structure: What is the earliest time you can finish activity D without delaying the project? Time Estimates (days) Activity Precedes

Consider the following work breakdown structure:

Consider the following work breakdown structure: What is the earliest time you can finish activity D without delaying the project? Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start AB CD 44 50 56 B D 45 60 75 E 42 45 48 D F 31 40 49 E F 27 36 39 F End 58 70 82 100