Question: . Consider the following work breakdown structure: What is the earliest time you can finish activity D without delaying the project? Time Estimates (days) Activity

. Consider the following work breakdown
. Consider the following work breakdown structure: What is the earliest time you can finish activity D without delaying the project? Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start AB A C D 44 50 56 B D 43 60 775 E 45 48 31 40 49 27 36 39 End 38 10 S2 CA th 140 100 96 131 201