Question: Consider the following work breakdown structure: Start Finish Duration (days) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 41 50 59 B 1
Consider the following work breakdown structure: Start Finish Duration (days) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 41 50 59 B 1 3 54 60 66 C 2 4 58 70 82 D 3 4 32 41 44 What is the probability that this project will be completed within 130 days? Multiple Choice .9987 .9772 .8413 .9544 .90
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
