Question: Consider the following work breakdown structure: Start Finish Duration (days) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 41 50 59 B 1
Consider the following work breakdown structure:
| Start | Finish | Duration (days) | |||||||||||||
| Activity | Node | Node | Optimistic | Most Likely | Pessimistic | ||||||||||
| A | 1 | 2 | 41 | 50 | 59 | ||||||||||
| B | 1 | 3 | 54 | 60 | 66 | ||||||||||
| C | 2 | 4 | 58 | 70 | 82 | ||||||||||
| D | 3 | 4 | 32 | 41 | 44 | ||||||||||
What is the estimated slack time for activity D?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock