Question: Consider the following work breakdown structure: Start Finish Duration (days) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 41 50 59 B 1

Consider the following work breakdown structure:

Start Finish Duration (days)
Activity Node Node Optimistic Most Likely Pessimistic
A 1 2 41 50 59
B 1 3 54 60 66
C 2 4 58 70 82
D 3 4 32 41 44

What is the estimated slack time for activity D?