Question: Consider the following work breakdown structure: Start Finish Duration ( days ) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 4 1 5

Consider the following work breakdown structure:
Start Finish Duration (days)
Activity Node Node Optimistic Most Likely Pessimistic
A 12415059
B 13546066
C 24587082
D 34324144
What is the probability that this project will be completed within 130 days?
Multiple Choice
.9544
.9987
.90
.9772
.8413
 Consider the following work breakdown structure: Start Finish Duration (days) Activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!