Question: Consider the following work breakdown structure: table [ [ Activity , Precedes, table [ [ Time Estimates ( days ) ] , [

Consider the following work breakdown structure:
\table[[Activity,Precedes,\table[[Time Estimates (days)],[Optimistic]],Most Likely,Pessimistic],[Start,A,B,C,-,-,-],[A,D,38,50,62],[B,E,90,99,108],[C,End,85,100,115],[D,F,19,25,31],[E,End,91,100,115],[F,End,62,65,68]]
What is the probability that this project will be completed within 205 days?
0.9544
0.6826
0.8413
0.9772
0.9987
 Consider the following work breakdown structure: \table[[Activity,Precedes,\table[[Time Estimates (days)],[Optimistic]],Most Likely,Pessimistic],[Start,A,B,C,-,-,-],[A,D,38,50,62],[B,E,90,99,108],[C,End,85,100,115],[D,F,19,25,31],[E,End,91,100,115],[F,End,62,65,68]] What

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!