Question: Consider the following work breakdown structure: table [ [ , , table [ [ Time Estimates ( days ) ] , [ Most

Consider the following work breakdown structure:
\table[[,,\table[[Time Estimates (days)],[Most]]],[Activity,Precedes,OptimisticLikelyPessimistic,,],[,A, B, C,-,-,62],[A,D,38,50,108],[B,E,90,99,115],[C,End,85,100,100],[D,F,19,25,31],[E,End,91,100,115],[F,End,62,65,68]]
What is the estimated expected (mean) time for project completion?
Multiple Choice
 Consider the following work breakdown structure: \table[[,,\table[[Time Estimates (days)],[Most]]],[Activity,Precedes,OptimisticLikelyPessimistic,,],[,A, B, C,-,-,62],[A,D,38,50,108],[B,E,90,99,115],[C,End,85,100,100],[D,F,19,25,31],[E,End,91,100,115],[F,End,62,65,68]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!