Question: Consider the following work breakdown structure: Activity Start Time Estimates (days) Optimistic Most Likely Pessimistic Precedes A,B,C D B End 38 90 85 19 91

Consider the following work breakdown structure:

Consider the following work breakdown structure: Activity Start Time Estimates (days) Optimistic Most Likely Pessimistic Precedes A,B,C D B End 38 90 85 19 91 62 50 99 100 25 100 65 62 108 115 31 115 68 D F E F End End What is the estimated expected (mean) time for project completion