Question: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start B D E F Precedes A,B,C D E End F

Consider the following work breakdown structure:

Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start B D E F Precedes A,B,C D E End F End End 38 90 85 19 91 62 30 99 100 25 100 65 62 108 115 31 115 68 What is the estimated expected (mean) time for project completion? 100 days 199 days 200 days 140 days 440 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!