Question: Consider the following work breakdown structure: Activity Start Node 1 1 2 3 Finish Node 2 3 4 4 Duration days) Most likely 50 60

Consider the following work breakdown structure:
Consider the following work breakdown structure: Activity Start Node 1 1 2 3 Finish Node 2 3 4 4 Duration days) Most likely 50 60 70 41 Optimistic 41 54 58 32 B D Pessimistic 59 66 82 44 What is the estimated expected (mean) time for activity D