Question: Consider the following work breakdown structure: Start Node Finish Node Activity A 1 Duration (days) Optimistic Most Likely 41 50 54 60 45 55 32

Consider the following work breakdown structure:

Consider the following work breakdown structure: Start Node Finish Node Activity A 1 Duration (days) Optimistic Most Likely 41 50 54 60 45 55 32 40 Pessimistic 59 66 B 1 3 2 4 75 D 3 4 45 What is the estimated standard deviation in the time for activity C? (Keep 1 decimal place)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!