Question: Multiple Choice 2 days 3 days 4 days 16 days 24 days Consider the following work breakdown structure: Activity Start ABCD D E F Precedes

Multiple Choice 2 days 3 days 4 days 16 days 24Multiple Choice 2 days 3 days 4 days 16 days 24

Multiple Choice 2 days 3 days 4 days 16 days 24 days Consider the following work breakdown structure: Activity Start ABCD D E F Precedes A, B, C D E End F End End Multiple Choice Optimistic I Time Estimates (days) Most Likely 38 90 85 19 91 62 50 99 100 25 100 65 What is the estimated standard deviation in the time for activity B? Pessimistic 62 108 115 31 115 68