Question: Consider the project described in the table below: Activity Duration Immidiate Predecessor A 5 - B 7 A C 4 A D 4 C E
Consider the project described in the table below:
| Activity | Duration | Immidiate Predecessor |
| A | 5 | - |
| B | 7 | A |
| C | 4 | A |
| D | 4 | C |
| E | 9 | B,D |
| F | 5 | C |
| G | 1 | E,F |
What is the critical path and the project duration?
Group of answer choices
A-C-D-E-G and 23 days
A-C-F-G and 19 days
A-B-E-G and 22 days
A-C-D-E-G and 21 days