Question: Consider the project described in the table below: Activity Duration Immidiate Predecessor A 5 - B 7 A C 4 A D 4 C E

Consider the project described in the table below:

Activity Duration Immidiate Predecessor
A 5 -
B 7 A
C 4 A
D 4 C
E 9 B,D
F 5 C
G 1 E,F

What is the critical path and the project duration?

Group of answer choices

A-C-D-E-G and 23 days

A-C-F-G and 19 days

A-B-E-G and 22 days

A-C-D-E-G and 21 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!