Question: Consider the project described in the table below: Activity Duration Immidiate Predecessor 5 7 A 4 A B D E F G 2 5 B.D

Consider the project described in the table
Consider the project described in the table below: Activity Duration Immidiate Predecessor 5 7 A 4 A B D E F G 2 5 B.D E,F 9 1 What is the critical path and the project duration? A-B-E-G and 22 days A-C-D-E-G and 21 days A-C-D-E-G and 23 days A-C-F-G and 19 days