Consider the project describe in the table below

Consider the project describe in the table below Activity Duration Immidiate Predesessor A 5 B 7 A st A | | || | D 3 B E 5 B, C D, E 1 What are the Earliest Start Times (EST) and Early Competition Times (ECT) for activity D? 14 and 17 12 and 15 9 and 12 O 12 and 14