Question: Consider the project described in the table below: Activity Duration Immidiate Predecessor 5 B 7 A A 4 D 5 B E 9 5 F

Consider the project described in the table

Consider the project described in the table below: Activity Duration Immidiate Predecessor 5 B 7 A A 4 D 5 B E 9 5 F B C.D E.F G 1 What is the earliest start time (EST) and latest start time (LST) of activity F? EST = 5 and LST = 12 EST = 5 and LST = 13 EST = 5 and LST = 5 EST = 5 and LST = 16