Question: Consider the project described in the table below: Activity Duration Immidiate Predecessor A B C D 5 7 10 2 4. 5 A B E

Consider the project described in the table
Consider the project described in the table below: Activity Duration Immidiate Predecessor A B C D 5 7 10 2 4. 5 A B E F B C,D E.F G 1 What is the earliest start time (EST) and latest start time (LST) of activity C? EST - 5 and LST - 13 EST- 5 and LST - 16 EST - 5 and LST - 12 EST - 5 and LST - 5