Question: Consider the project information in the table below, and draw and analyze a project network to answer the following sub-questions. Task Duration (days) Immediate Predecessors

Consider the project information in the table below, and draw and analyze a project network to answer the following sub-questions.

Task Duration (days) Immediate Predecessors

A3- B6- C1A D2B E1B F5E G 6 C,D,F H2E

  1. (1) Find the Early Start / Early Finish Time of Each Activity

  2. (2) Find the Late Start / Late Finish Time of Each Activity

  3. (3) Calculate the SLACK in each activity

  4. (4) Identify the critical path