Question: Consider the project information in the table below, and draw and analyze a project network to answer the following sub-questions. Task Duration (days) Immediate Predecessors
Consider the project information in the table below, and draw and analyze a project network to answer the following sub-questions.
Task Duration (days) Immediate Predecessors
A3- B6- C1A D2B E1B F5E G 6 C,D,F H2E
-
(1) Find the Early Start / Early Finish Time of Each Activity
-
(2) Find the Late Start / Late Finish Time of Each Activity
-
(3) Calculate the SLACK in each activity
-
(4) Identify the critical path