Question: Consider the project performance report presented in Figure 1 4 - 1 . What valid conclusion can you draw regarding the project cost performance as

Consider the project performance report presented in Figure 14-1. What valid conclusion can you draw regarding the project cost performance as of October 31,20XX?
The project is $8,000 over budget.
The project is $18,000 over budget.
The project is on budget.
The project is $26,000 under budget