Question: Consider the project performance report presented in Figure 14-1. What valid conclusion can you draw regarding the project cost performance as of October 31, 20XX?
Consider the project performance report presented in Figure 14-1. What valid conclusion can you draw regarding the project cost performance as of October 31, 20XX? O The project is on budget. The project is $26,000 under budget. O The project is $8,000 over budget. O The project is $18,000 over budget