Question: Considering the following data: Activity Preceding Activity Estimated in Units Start 0 D Start 7 A Start 9 F D, A 10 E D 11
Considering the following data:
| Activity | Preceding Activity | Estimated in Units |
| Start |
| 0 |
| D | Start | 7 |
| A | Start | 9 |
| F | D, A | 10 |
| E | D | 11 |
| G | F, E | 7 |
| B | F | 11 |
| H | G | 13 |
| C | H | 7 |
| M | H | 12 |
| N | G | 8 |
| P | F | 10 |
| End | C, B, M, N, P | 0 |
Answer the following questions:
- What is the duration of the critical path?
- What is the float of activity B?
- What is the float of activity E?
- What is the float of activity D?
- What is the float of activity N?
- What is the closest duration path to the critical path?
- Can a project have two critical paths? If so what does this do to risk for the project? Explain your answer.