Question: Activity Preceding Activity Estimate in Months Start 0 D Start 4 A Start 6 F D,A 7 E D 8 G F,E 5 B F
| Activity | Preceding Activity | Estimate in Months |
| Start | 0 | |
| D | Start | 4 |
| A | Start | 6 |
| F | D,A | 7 |
| E | D | 8 |
| G | F,E | 5 |
| B | F | 5 |
| H | G | 7 |
| C | H | 8 |
| End | C,B | 0 |

draw the diagram above and fill in the numbers used.. Show all steps and work out
show all steps and the diagram draw on a piece of paper
Answer all the following questions
1. What is the duration of the critical path?
2. What is the float of activity B?
3. What is the float of Activity E?
4. What is the float of Activity D?
5. To shorten the length of the project, the sponsor has offered to remove the work of activity E from the project, making activity D the predecessor to activities G and F. What will be the effect?