Question: PROBLEM FOUR: CONSIDERING THE FOLLOWING DATA: Activity Preceding Activity Estimated in Units Start 0 D Start 4 A Start 6 F D, A 7 E

PROBLEM FOUR: CONSIDERING THE FOLLOWING DATA:

PROBLEM FOUR: CONSIDERING THE FOLLOWING DATA: Activity Preceding Activity Estimated in Units Start 0 D Start 4 A Start 6 F D, A 7 E D 8 G F, E 5 B 5 H G 7 C H 8 End CB 0 ANSWER THE FOLLOWING QUESTIONS: (a) What is the duration of the critical path? (b) What is the float of activity B? (c) What is the float of activity E? (d) What is the float of activity D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock