Question: Considering the network diagram below. If Task C takes 1 5 days instead of 1 0 , which af the following is true? A .

Considering the network diagram below. If Task C takes 15 days instead of 10, which af the following is true?
A. The critical path takes 60 days.
B. The critical path takes 0 days.
c. The critical path increases by 5 days.
D. The critical path changes to 55 days.
 Considering the network diagram below. If Task C takes 15 days