Question: Crash cost (slope), maximum crash time, normal time, and normal cost are provided below. The indirect costs for each project duration are: $550 (20 time

Crash cost (slope), maximum crash time, normal
Crash cost (slope), maximum crash time, normal time, and normal cost are provided below. The indirect costs for each project duration are: $550 (20 time units), $400 (19), $350 (18), $100 (17), and $50 (16). Crash Max. Activity Cost Crash (Slope) Time 1 2 A B C D E F G H I 25 75 0 20 65 105 40 0 200 0 1 3 1 1 0 1 Normal Normal Time Cost 6 4 5 3 6 3 6 3 5 70 90 100 80 100 140 80 90 210 A B C D E F G H Calculate the initial total cost (direct + indirect cost) before crashing the project