Question: Create a precedence diagram/activity model to understand all activities, dependencies, and duration. Create the diagram on LucidCharts and save as a PDF. Perform a forward

  • Create a precedence diagram/activity model to understand all activities, dependencies, and duration. Create the diagram on LucidCharts and save as a PDF.

    • Perform a forward pass and backwards pass

    • Calculate the float/slack

    • Identify the critical path

Google is developing a new app called Backup & Sync (BS) that allows users to backup and sync their files from all their devices. This system provides files to be available to the users across all their devices. You drew out the business process a few months ago, now the project lead has written tasks that would need to be completed in order to build the platform. Your task is to create the project map (i.e., precedence diagram model)

Activity ID

Activity

Predecessor Activity

Duration (days)

1

Develop oAuth connection to Google login portal to allow users to login or signup page

-

2

2

Develop UI wireframes

1

3

3

Add functionality to the wireframe of the platform

2

14

4

Allocate server storage from Google Cloud team

1

3

5

Connect cloud storage with functional BS platform

3, 4

5

6

Test BS platform

5

3

7

Perform fixes from testing

6

7

8

User testing with users that signed up from beta program

6

14

9

Perform fixes from user testing

8

7

10

Install on servers and launch to public

9,7

1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!