Question: CTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 3 B A 5 C A 4 D B 2 E C D 3 F D 1
CTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D B
E C D
F D
G F
H E G
b What is the critical path?
multiple choice
ACEH
ABDEH
ABDFGH
ACEFGH
c How many weeks will it take to complete the project?
d Which activities have slack, and how much?
multiple choice
CPicture weeksPicture FPicture weekPicture GPicture week.
APicture weekPicture BPicture weeksPicture DPicture weeks.
BPicture weeksPicture DPicture weeksPicture EPicture weeks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock