Question: CTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 3 B A 5 C A 4 D B 2 E C D 3 F D 1

CTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 5
C A 4
D B 2
E C D 3
F D 1
G F 1
H E G 4
b. What is the critical path?
multiple choice 1
A-C-E-H
A-B-D-E-H
A-B-D-F-G-H
A-C-E-F-G-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
multiple choice 2
CPicture 3 weeksPicture FPicture 1 weekPicture GPicture 1 week.
APicture 1 weekPicture BPicture 2 weeksPicture DPicture 4 weeks.
BPicture 3 weeksPicture DPicture 2 weeksPicture EPicture 4 weeks.