Question: Problem 5-8 Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 5 C A 4 D B 3 E

Problem 5-8

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 5
C A 4
D B 3
E C%media:cm.png% D 6
F D 4
G F 3
H E%media:cm.png% G 5

b. What is the critical path?

A) A-B-D-F-G-H

B) A-B-D-E-H

C) A-C-E-H

D) A-C-E-F-G-H

c. How many weeks will it take to complete the project?

Number of weeks __________

d. Which activities have slack, and how much?

  • E 1 week H 3 weeks.
  • C 5 weeks E 1 week.
  • B 2 weeks D 1 week.