Problem 5-8
Schedule the following activities using CPM:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 3 | |
| B | A | 5 |
| C | A | 4 |
| D | B | 3 |
| E | C%media:cm.png% D | 6 |
| F | D | 4 |
| G | F | 3 |
| H | E%media:cm.png% G | 5 |
b. What is the critical path?
A) A-B-D-F-G-H
B) A-B-D-E-H
C) A-C-E-H
D) A-C-E-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks __________
d. Which activities have slack, and how much?
- E 1 week H 3 weeks.
- C 5 weeks E 1 week.
- B 2 weeks D 1 week.