Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 5 C A 4 D B 3 E C%media:cm.png% D

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 5
C A 4
D B 3
E C%media:cm.png% D 6
F D 4
G F 3
H E%media:cm.png% G 5
  1. What is the critical path?

    multiple choice 1
    • A-C-E-F-G-H

    • A-B-D-E-H

    • A-C-E-H

    • A-B-D-F-G-H

  2. How many weeks will it take to complete the project?

  3. Which activities have slack, and how much?

    multiple choice 2
    • C 5 weeks E 1 week.

    • B 2 weeks D 1 week.

    • E 1 week H 3 weeks.