Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 5 C A 4 D B E C.D F D

Schedule the following activities using CPM:

Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 5 C A 4 D B E C.D F D F H E.G b. What is the critical path? O A-C-E-H mmin O E. 1 week 3 6 4 3 5 A-B-D-E-H A-B-D-F-G-H O A-C-E-F-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? B. 2 weeks Picture D. 1 week. C. 5 weeks Picture E. 1 week. Picture H. 3 weeks