Question: ctivityABCDEFGHIJPredecessorsAAACBEE,FDG , H , IDuration ( days ) 6 6 5 8 1 6 1 0 9 1 7 1 4 2 Conduct both a
ctivityABCDEFGHIJPredecessorsAAACBEE,FDGHIDuration days Conduct both a forward and backward pass using AON notation. What is the estimated total durationfor the project?Identify all paths through the network. Which is the critical path?Which activities have slack time?Identify all burst activities and merge activities.