Question: D Description Predecessor Time(days) A Systems None 8 B Subsystem A design A 5 C Subsystem B design A 4 D Subsystem C design A
D Description Predecessor Time(days) A Systems None 8 B Subsystem A design A 5 C Subsystem B design A 4 D Subsystem C design A 5 E Program A B 3 F Program B C 10 G Program C D 3 H Subsystem A test E 1 I Subsystem B test F 1 J Subsystem C test G 1 K Integration H, I, J 4 L Integration test K 5 What is the total slack on D? 1 What is the total slack on E? What is the FREE slack on B? What is the FREE slack on H?