Question: d . How many weeks could activity F be delayed without delaying the project? e . What is the critical path? Enter the activities in

d. How many weeks could activity F be delayed without delaying the project?
e. What is the critical path? Enter the activities in capital letters with hyphens (but no spaces) separating the activities. For example, A-C-G.
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 11
B A 12
C A 9
D B 5
E B 10
F D 9
G C, E 5
H F, G 10
I G, H 9