Question: e. What is the critical path? Enter the activities in capital letters with hyphens (but no spaces) separating the activities. For example, A-C-G . IMMEDIATE

e. What is the critical path? Enter the activities in capital letters with hyphens (but no spaces) separating the activities. For example, A-C-G.
IMMEDIATE PREDECESSOR ACTIVITY B D E F G H I A A B B D C, E F G G H TIME (WEEKS) 8 10 23 5 10 8 5 10 9 a. What is the early start date for activity H? ES for H b. What is the late finish date for activity B? LF for B c. Determine the minimum number of weeks for completing the project. Minimum number of weeks d. How many weeks could activity F be delayed without delaying the project? Slack (in weeks)Step by Step Solution