Question: Determine the minimum number of weeks for completing the projectHow many weeks could activity F be delayed without delaying the project?Assuming there are no delays

Determine the minimum number of weeks for completing the projectHow many weeks could activity F be delayed without delaying the project?Assuming there are no delays (question part e is independent of question part d) or crashing, what is the critical path? Enter the activities in capital letter to its hyphens (but no spaces) separating the activities

Determine the minimum number of weeks for completing the projectHow many weeks

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 8 A 10 5 10 8 C, E 5 F, G G, H