Question: Danny is conducting PERT analysis for a project network. He finds that the activities A, B, C, D, E, F, G,H, and I are on

Danny is conducting PERT analysis for a project
Danny is conducting PERT analysis for a project network. He finds that the activities A, B, C, D, E, F, G,H, and I are on the critical path. He also determines that the activities A, B, C, D, E, F, G, H, and I have standard deviations of 1,2,4,2,6,2,4,6, and 2 weeks, respectively. Find the STANDARD DEVIATION of the critical path A-B-C-D-E-F-G-H-I. 1.79505 weeks 3.22222 weeks 11 weeks 29 weeks 5.38516 weeks