Question: Define project duration, critical path, critical and non-critical activities Activity Code Predecessor Activity Duration, weeks A - 3 B - 2 C - 5 D
- Define project duration, critical path, critical and non-critical activities
| Activity Code | Predecessor | Activity Duration, weeks |
| A | - | 3 |
| B | - | 2 |
| C | - | 5 |
| D | A | 2 |
| E | 4 | |
| F | B | 10 |
| G | 8 | |
| H | 7 | |
| I | F, G | 6 |
| J | , | 4 |
| D, H | 10 |