Question: Find the project duration & critical path: Activity Duration (Weeks) Immediate Predecessors A 10 B 4 C 6 D 4 B E 1 C,D F
Find the project duration & critical path: Activity Duration (Weeks) Immediate Predecessors A 10 B 4 C 6 D 4 B E 1 C,D F 4 C G 4 A,D H 5 E,F Project Schedule Path Duration A-G 10+4 = 14 weeks B-D-G 4+4+4 = 12 weeks B-D-E-H 4+4+1+5 = 14 weeks C-E-H 6+1+5 = 12 weeks C-F-H 6+4+5 = 15 weeks If C-F-H is the critical path at 15 weeks. Using the network diagram and project schedule that you created. Identify what the Earliest Start Time (ES) would be for Activity "E"