Question: Define project duration, critical path, critical and non-critical activities Activity Code Predecessor Activity Duration, weeks A - 3 B - 4 C A 2 D
- Define project duration, critical path, critical and non-critical activities
| Activity Code | Predecessor | Activity Duration, weeks |
| A | - | 3 |
| B | - | 4 |
| C | A | 2 |
| D | A | 4 |
| E | B | 6 |
| F | B | 3 |
| G | B | 5 |
| H | D, E | 5 |
| I | C, H | 7 |
| J | F, G, H | 2 |