Question: Determine the Critical Path given the following information: Activity Time Precedence Activities A 3 None B 5 None C 2 A D 6 C AND
Determine the Critical Path given the following information:
| Activity | Time | Precedence Activities |
| A | 3 | None |
| B | 5 | None |
| C | 2 | A |
| D | 6 | C |
| AND | 5 | C |
| F | 3 | AND |
| G | 4 | B,C |
| H | 3 | D,G,F |
| I | 4 | D,F |
| J | 2 | H |
| K | 2 | I,J |
If the Optimistic, Most Likely, and Pessimistic times for Activity I were 2,4, and 12, what would happen?