Question: Determine the Critical Path given the following information: Activity Time Precedence Activities A 3 None B 5 None C 2 A D 6 C AND

Determine the Critical Path given the following information:

Activity Time

Precedence

Activities

A 3 None
B 5 None
C 2 A
D 6 C
AND 5 C
F 3 AND
G 4 B,C
H 3 D,G,F
I 4 D,F
J 2 H
K 2 I,J

If the Optimistic, Most Likely, and Pessimistic times for Activity I were 2,4, and 12, what would happen?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To determine the critical path we need to calculate the earliest start time ES earliest finish time ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!