Question: Determine the Critical Path given the following information: Activity Time Precedence Activities A 3 None B 5 None C 2 A,B D 6 C E
Determine the Critical Path given the following information:
| Activity | Time | Precedence Activities |
| A | 3 | None |
| B | 5 | None |
| C | 2 | A,B |
| D | 6 | C |
| E | 5 | C |
| F | 3 | E |
| G | 4 | C |
| H | 3 | D,G,F |
| I | 4 | D,F |
| J | 2 | H |
| K | 2 | I,J |
Can you guys draw out the critical path but not in excel? thanks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
